Pittmann,
Brooksbank, Panter & Dreyer Road Improvements – 2004 Pittmann, Brooksbank, Panter and Dreyer were
approved for resurfacing work through the 2004 Capital Budget process.
The contract of $468,289.27 for this work has been approved by
Council. Due to the early preparation and tender calls,
significant cost savings resulted which has allowed for the advancement
to this year for similar work to also be
done on Dreyer Drive
between Clements and Pickering Beach Road. Council has provided approval
for a budget in the amount of $130,000.00 for Dreyer. This resurfacing also includes replacement of curbs
and sidewalks as well as roadway sub drains. The roadwork is expected to begin May 10th
and completed by no later than July 23rd. This road work should provide an additional 15 years life expectancy to these roads. Road resurfacing done in a timely fashion can avoid extensive future costs for road replacements.
|